PV Project Report: Dogana (52MW)
- Nova Rise Group

- Nov 1, 2025
- 4 min read

Project Overview
Dogana A was a 15 MW utility-scale solar tracker project where our team was responsible for both electrical and mechanical installation works.
Because the project used tracker structures, the execution required a high level of accuracy, alignment control, and careful coordination across difficult terrain. Tracker PV projects are more demanding than standard fixed-tilt installations because the structure must be installed precisely to allow proper operation and long-term reliability.
Despite the challenging terrain and the precision required for tracker installation, our team completed the project 2.5 months earlier than the original schedule.
Dogana A is a strong example of our work as a solar tracker installation partner for EPC companies that require reliable execution, accurate mechanical works, and coordinated electrical installation on utility-scale PV projects.
Project Data
Item | Details |
Project name | Dogana A |
Project type | Utility-scale solar tracker project |
Scope | Electrical and mechanical installation works |
Initial awarded scope | 15 MW |
Final awarded scope | 15 MW |
Man-hours | 9,000 |
HSE incidents | 1 minor incident |
Main difficulties | Difficult terrain requiring precise tracker installation |
Machinery used | 2 excavators, 2 telehandlers, 1 ramming machine, 3 bobcats |
Schedule result | Completed 2.5 months earlier than the original schedule |
Scope of Work
Our scope on Dogana A covered the electrical and mechanical execution of a 15 MW tracker PV project.
The mechanical works required accurate ramming, tracker structure installation, alignment control, and careful coordination with the terrain conditions. The electrical works were executed in parallel with the mechanical progress, allowing the project to move efficiently toward completion.
The scope included:
Mechanical installation for tracker PV structures
Tracker structure installation
Ramming works
Electrical installation works
Material handling
Site logistics
Machinery coordination
Work-front organization
Quality-focused execution on difficult terrain
This combination of tracker mechanical installation and electrical works required disciplined planning and precise execution throughout the project.
Main Site Challenge: Tracker Installation on Difficult Terrain
The main difficulty on Dogana A was the terrain. The site required a lot of precise work to complete the tracker installation correctly.
In a tracker PV project, installation accuracy is critical. If the structure is not positioned and aligned correctly, it can affect later assembly, commissioning, and long-term system operation.
For this reason, the team had to maintain close attention to:
Correct pile positioning
Ramming accuracy
Tracker structure alignment
Installation tolerances
Material movement across difficult terrain
Coordination between mechanical and electrical teams
Safe machinery operation in challenging site conditions
This type of project requires more than basic solar installation capacity. It requires an experienced PV tracker installation partner that understands the level of precision needed for tracker-based utility-scale solar projects.
Execution Approach
To manage the terrain and tracker requirements, our team followed a structured execution approach. The focus was on maintaining both installation speed and technical accuracy.
The execution approach included:
Careful sequencing of mechanical works
Accurate ramming and structure positioning
Organized material distribution across the site
Efficient coordination of excavators, telehandlers, ramming equipment, and bobcats
Continuous attention to tracker alignment and installation quality
Parallel progress between mechanical and electrical teams
This approach helped the team manage the difficult site conditions while maintaining strong productivity.
Machinery and Site Resources
Dogana A was completed using machinery suitable for utility-scale tracker PV installation and electrical/mechanical works.
Machinery used on site included:
2 excavators
2 telehandlers
1 ramming machine
3 bobcats
This machinery setup supported site preparation, ramming, material handling, equipment movement, and daily installation activities. Because of the difficult terrain, machinery coordination was important for both productivity and safe execution.
Man-Hours and Productivity
The project involved approximately 9,000 man-hours.
These man-hours covered the electrical and mechanical installation scope, including the precise work required for tracker installation. Completing a 15 MW tracker PV project on difficult terrain 2.5 months ahead of the original schedule demonstrates strong productivity, site organization, and execution control.
For EPC companies, this is a key indicator of a reliable execution partner: the ability to deliver technically demanding work safely, accurately, and faster than planned.
Health and Safety
During the Dogana A project, one minor incident was recorded.
The project involved difficult terrain, heavy machinery, tracker installation works, and electrical and mechanical activities. Under these conditions, maintaining controlled site execution and safe machinery coordination was an important part of the project delivery.
Problems and Solutions
No major execution issues were recorded on Dogana A.
The main challenge was the difficult terrain and the precision required for tracker installation. This was managed through careful work-front organization, accurate mechanical execution, proper machinery coordination, and close attention to installation quality.
The result was a smooth execution process and completion significantly ahead of the original schedule.
Photos and Videos from the Project
Photos and videos from Dogana A can be used to show the terrain, tracker installation works, machinery, and project progress.
Recommended media to include:
Tracker structure installation
Difficult terrain areas
Ramming activities
Excavators, telehandlers, and bobcats operating on site
Electrical installation works
Mechanical installation progress
Completed tracker rows
General site overview
Before-and-after progress photos

Final Result
Dogana A was completed as a 15 MW electrical and mechanical solar tracker project.
The main difficulty was the terrain, which required precise work for tracker installation. Despite this challenge, our team completed the project 2.5 months earlier than the original schedule.
The project was delivered with:
15 MW electrical and mechanical scope
9,000 man-hours
1 minor HSE incident
Difficult terrain managed successfully
Precise tracker installation work
Completion 2.5 months ahead of schedule
For EPC companies looking for a reliable solar tracker installation partner, Dogana A demonstrates our ability to deliver electrical and mechanical PV works with precision, speed, and strong site organization.
Summary
Dogana A highlights our experience in utility-scale solar tracker projects where terrain and installation precision are key execution factors.
Key results:
15 MW electrical and mechanical installation scope
Utility-scale solar tracker project
Tracker installation on difficult terrain
9,000 man-hours delivered
2 excavators, 2 telehandlers, 1 ramming machine, and 3 bobcats used
1 minor HSE incident recorded
No major execution issues
Project completed 2.5 months earlier than the original schedule
Dogana A reflects the value we bring as a PV execution partner: precision, speed, site organization, and reliable delivery under demanding terrain conditions.


