Project Update: EG BANDO D’ARGENTA: Strong construction progress.

Updated: 5 days ago

Nova Rise Group continues to deliver strong construction progress at the EG Bando d’Argenta solar project in Italy. Over the past 40 days, our teams have maintained a consistent pace of execution, advancing structural installation, piling, module mounting and electrical infrastructure works in parallel.
The project represents another example of our approach to utility-scale PV construction: combining dedicated personnel, an in-house machinery fleet and coordinated mechanical and electrical operations to maintain productivity across multiple work fronts.
An important development during this period was the approval of an additional 15 MW electrical grant, expanding the original electrical scope and bringing the total electrical allocation to 65 MW.
Below is an overview of the project scope, construction progress and resources currently deployed on site.
1. PROJECT OVERVIEW
EG Bando d’Argenta involves the installation of a utility-scale photovoltaic facility, with Nova Rise Group undertaking both mechanical and electrical construction activities.
The project combines a fixed-tilt mounting system with high-power JA Solar modules, requiring coordinated piling, structural assembly, module installation and extensive electrical infrastructure works.
Project Specification | Details |
Location | Bando d’Argenta, Italy |
Initial Mechanical Scope | 50 MW |
Initial Electrical Scope | 50 MW |
Additional Electrical Grant | 15 MW |
Total Electrical Scope | 65 MW |
Mounting Structure | Gonvarri – Fixed Tilt |
PV Modules | JA Solar Full Black |
Module Power | 625–630 Wp |
The additional electrical allocation represents an expansion of the original project scope and further demonstrates the importance of maintaining sufficient execution capacity across the electrical work packages.
2. MECHANICAL INSTALLATION – 50 MW
Mechanical works have progressed particularly well over the past 40 days. Our teams have completed approximately 50% of the fixed-structure installation, alongside significant progress in piling and module mounting.
The piling operation has reached an average production rate of approximately 1,000 piles per day, while module installation has reached daily production of up to 1,000 modules.
These results reflect the coordination between piling operations, material handling and structural assembly, allowing different activities to advance simultaneously without compromising the overall construction sequence.
Mechanical Progress – Last 40 Days
Work Package | Achieved Progress | Production Rate |
Fixed Structure – Gonvarri | 25 MW (50%) | — |
Pile Installation | 31,000 piles | >1,000/day |
PV Module Installation | 4,000 modules | >1,000/day |
Maintaining these production rates requires more than machinery alone. It depends on effective logistics, material availability, equipment utilisation and coordination between the individual installation teams. These are essential elements of Nova Rise Group's execution approach on utility-scale projects.

3. ELECTRICAL WORKS – 65 MW
In parallel with the mechanical installation, our electrical teams have been advancing the underground infrastructure and cable installation works.
The electrical scope involves extensive trenching, conduit placement, cable routing and earthing activities. Coordinating these operations alongside the mechanical installation is essential to keeping the different construction work fronts aligned and avoiding unnecessary delays between installation phases.
Over the reporting period, substantial quantities of electrical infrastructure have been completed, including 9 km of LV/MV trenching and significant cable installation volumes.
Electrical Progress – Completed Quantities
Work Package | Completed Quantity |
LV & MV Trenching | 9 km |
BT Cable Installation | 80 km |
Corrugated Pipe Installation | 50 km |
MV Cable Installation | 10 km |
Earthing Cable Installation | 110 km |
Our electrical teams have also achieved solar cable installation rates of up to 10 km per day, demonstrating the capacity to sustain high-volume installation activities across the site.
The simultaneous development of trenching, cable routing and earthing infrastructure is an important part of the project's overall execution strategy, allowing the electrical work packages to progress alongside the mechanical installation rather than becoming a bottleneck at later stages.

4. MACHINERY & RESOURCES DEPLOYED
To support the scale and pace of construction, Nova Rise Group has mobilised a dedicated machinery fleet, providing the equipment required for piling, earthworks, material handling and installation activities.
On-Site Machinery
Equipment | Quantity | Main Application |
Piling / Ramming Machines | 2 | Foundation piling |
Telehandlers | 2 | Material handling and structural logistics |
Skid Steer Loaders | 5 | Site preparation and material distribution |
9-Ton Excavators | 2 | Earthworks and trenching |
The availability of dedicated machinery on site allows our teams to maintain operational flexibility and coordinate multiple activities across different sections of the project.
Combined with our own workforce and established construction management processes, this deployment provides the operational foundation needed to sustain the production levels achieved at Bando d’Argenta.

5. EXECUTION PERFORMANCE & PROJECT OUTLOOK
The progress achieved over the past 40 days reflects the strength of the construction operation currently deployed at EG Bando d’Argenta.
With 25 MW of fixed structures installed, 31,000 piles completed and significant volumes of electrical infrastructure already in place, the project continues to advance across its main construction work packages.


What makes this progress particularly important is the simultaneous execution of mechanical and electrical activities. Maintaining productivity across both disciplines requires effective work-front planning, equipment coordination, material logistics and consistent site management.
The approval of the additional 15 MW electrical grant also expands the project's scope, reinforcing the importance of maintaining the resources and execution capacity required for the next stages.
For Nova Rise Group, EG Bando d’Argenta is another opportunity to demonstrate our capabilities as a utility-scale PV construction partner, delivering mechanical and electrical work packages through dedicated teams, our own machinery fleet and hands-on project execution.



We remain focused on maintaining construction momentum, delivering the upcoming milestones and continuing to build a strong track record across Europe's utility-scale solar market.
More progress to follow.


