Project Update: EG ALBA Hits 75% Completion

Writer: Nova Rise Group
Nova Rise Group
Aug 3
1 min read

Updated: Aug 31

Working on sloping, irregular terrain introduces significant logistical friction to material distribution and mechanical alignment. Despite these challenging site conditions, the Novarise Group team at EG ALBA has delivered rapid progress.  

In just 40 days, a specialized crew of 21 professionals has brought the overall project execution to 75% completion.



Site Progress Breakdown

The focused deployment of our lean crew on-site has allowed us to hit key installation milestones cleanly across the site:

  • Ramming: 100% Complete — All foundation piles are fully driven and locked into position.

  • Structure Assembly: 90% Complete — Torque tubes and fixed framework are nearly fully aligned across the sloped grid.

  • Module Installation: 50% Complete — Half of the PV modules are fully mounted and secured.

Construction Workstream

Status

Details

Foundation Piling / Ramming

100%

All piles completed on schedule.

Structural Alignment

90%

Final structural framework underway.

PV Module Mounting

50%

Rapid mounting sequence active.

Overall Project Completion

75%

Delivered in 40 days with a 21-person crew.

Expanded Scope: Awarded an Additional 10 MW

Performance on tough ground builds long-term trust. Originally contracted for a 6 MW installation, Novarise Group’s execution speed and site management prompted the client to award an additional 10 MW extension. 


This brings the expanded total scope of EG ALBA to 16 MW. 

 
 