Nova Rise Group Launches 50 MWp Bando D’Argenta Project in Ferrara.

Writer: Nova Rise Group
Nova Rise Group
Aug 14
2 min read

We are proud to announce another major milestone in our utility-scale portfolio. Novarise Group has officially signed contracts with Enfinity to deliver the full mechanical and electrical scope for Bando D’Argenta—a massive 50 MWp solar installation located in the province of Ferrara, Italy.

True to our commitment to rapid project execution, contract execution and site mobilization are happening simultaneously. As of August 24, 2026, our engineering, logistics, and site crews are deployed on-ground to kick off the 6-month construction sequence.


Project Snapshot: Bando D’Argenta

Key Metric / Parameter

Project Detail

Project Name

Bando D’Argenta

Capacity

50 MWp

Investor / EPC Partner

Enfinity

Location

Ferrara, Italy

Scope of Work

Full Scope (Mechanical & Electrical)

Structure System

Fixed Structure (Solar Steel)

Mobilization Date

August 24, 2026

Contract Duration

6 Months


Mastered Site Engineering: Navigating Former Rice Fields & Underground Water


Every utility-scale site presents distinct geotechnical characteristics. The Bando D’Argenta footprint is situated on a former rice field characterized by a high underground water table and saturated soil profile.

Managing construction across high-moisture agricultural land demands tailored engineering techniques:

  • Foundation Engineering: Utilizing robust Solar Steel fixed structures, our piling strategy accounts for high moisture levels to deliver long-term load-bearing stability.

  • Trenching & Dewatering Coordination: Our electrical teams are executing specialized subterranean cable routing strategies, using continuous dewatering and reinforced trench designs to secure low and medium-voltage networks.

  • Heavy Equipment Logistics: Broad-track machinery and optimized access roads are being deployed to prevent site compaction and maintain continuous productivity regardless of ground moisture.


Complete Mechanical & Electrical Execution


Executing a 50 MWp footprint within a strict 6-month timeframe requires seamless coordination between mechanical assembly and electrical installation. Because Novarise Group manages both scopes under one umbrella, we eliminate the friction, delays, and interface risks that typically occur between separate contractors.

Over the next 180 days, our integrated workflow will cover:

  1. Civil & Ground Preparation: Soil stabilization, drainage layout, and access roading.

  2. Mechanical Buildout: Piling, fixed Solar Steel frame installation, and PV module mounting.

  3. Electrical Infrastructure: Trenching, DC/AC cabling, inverter station integration, and MV grid connection prep.


Delivering Clean Energy for Ferrara


Our collaboration with Enfinity on the Bando D’Argenta project underscores a shared commitment to building resilient, high-yield clean energy infrastructure across Europe. With crews and machinery already active on-site in Ferrara, we are ready to drive this 50 MWp build to completion on schedule.

Stay tuned for our upcoming progress updates as piling and structural assembly get under way!

 
 